CHARLES R. SIMPSON, III, Judge.
This action involves a procedure known as "mitigation banking," an environmental preservation activity supposedly designed to protect the nation's wetlands. In accordance with the Clean Water Act, 33 U.S.C. § 1251 et seq., the United States Army Corps of Engineers (the "Corps") requires that persons or business whose activities will adversely impact wetlands in one place compensate for the damage by establishing a new wetland elsewhere that will replace any lost biological functions. "Mitigation banking" is one way a person or entity can fulfill this demand: It pays a third party (a mitigation bank) to create a new wetland
The facts of this case have been set out at some length in our prior opinions. Id. We therefore provide only an abbreviated version here. Dr. Darroll Hawkins owns Highview Engineering, Inc., a Kentucky environmental engineering firm. The Wetland Bank of Kentucky ("WBK"), in which Highview was a partner, was party to a contract with the Corps. WBK apparently failed in its duties under that contract, and the Corps sued for breach of contract and of the duty of good faith, negligent misrepresentation, and unjust enrichment. The parties settled the Corps' claims for $70,000, and a Consent Judgment was entered on March 30, 2006.
In April 2007, Hawkins began working with Dr. Phillip J. Harris, an environmental enhancement entrepreneur, to develop a proposal for a new wetlands project involving the Corps. Hawkins submitted the proposal on Harris's behalf. Approximately 9 ½ months later, after a number of unsuccessful attempts to contact the Corp regarding the status of the proposal, a Corps Project Manager, Katie McCafferty, contacted Harris to discuss the proposal and a meeting was scheduled for April 3, 2008 with Harris, Hawkins and McCafferty slated to attend. The morning prior to the meeting, Harris received a cell phone call from McCafferty asking to meet with him that day. They met at Cracker Barrel Restaurant in Paducah, Kentucky, shortly after the call. Hawkins was not invited to attend that meeting. At the meeting outside restaurant, McCafferty allegedly informed Hawkins that Ann Nunn, an attorney with the Corps, had stated that (according to the complaint) "she did not want any wetlands mitigation bank proposals in which Dr. Hawkins played a role." (Compl. ¶ 17.) Harris was also allegedly informed that other Corps employees were "uncomfortable" with having Hawkins involved in any new projects, and it was "suggested" that Harris hire a different consultant. (Id.) The meeting with Hawkins, Harris and McCafferty scheduled for the following day did not occur. Harris purportedly took McCafferty's suggestion and ended his business relationship with Hawkins. Additionally, the Corps also allegedly removed Hawkins and Highview from its published "Wetland Consultant List."
Hawkins and his company filed suit alleging four causes of action: violation of their Fifth Amendment right to due process of law; violation of their First Amendment right to freedom of association, interference with prospective and existing contractual relationships; and defamation. The first two claims were alleged against both defendants; the latter two were asserted only against Nunn in her individual capacity.
In a prior opinion and order, 2010 WL 2106664, 2010 U.S. Dist. LEXIS 50987 (W.D.Ky. May 24, 2010), the court dismissed all of the plaintiffs' complaint with the exception of Count I, as asserted against the Corps, alleging that the plaintiffs were de facto debarred from doing business with the Corps without receiving constitutionally guaranteed procedural
We previously found that the plaintiffs' debarment claim in this case had "at least some superficial appeal" on the merits, id. at *6, 2010 U.S. Dist. LEXIS 50987 at *18, slip op. at 11, and we held that this court had jurisdiction to entertain the claim. (DN 35). The parties have now filed cross-motions for summary judgment on this remaining claim.
A party moving for summary judgment has the burden of showing that there are no genuine issues of fact and that the movant is entitled to summary judgment as a matter of law. Adickes v. S.H. Kress & Co., 398 U.S. 144, 151-60, 90 S.Ct. 1598, 26 L.Ed.2d 142 (1970); Felix v. Young, 536 F.2d 1126, 1134 (6th Cir.1976). Not every factual dispute between the parties will prevent summary judgment. The disputed facts must be material. They must be facts which, under the substantive law governing the issue, might affect the outcome of the suit. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986). The dispute must also be genuine. The facts must be such that if they were proven at trial, a reasonable jury could return a verdict for the non-moving party. Id. at 2510. The disputed issue does not have to be resolved conclusively in favor of the nonmoving party, but that party is required to present some significant probative evidence which makes it necessary to resolve the parties' differing versions of the dispute at trial. First National Bank of Arizona v. Cities Service Co., 391 U.S. 253, 288-89, 88 S.Ct. 1575, 20 L.Ed.2d 569 (1968). The evidence must be construed in a light most favorable to the party opposing the motion. Bohn Aluminum & Brass Corp. v. Storm King Corp., 303 F.2d 425 (6th Cir.1962).
Plaintiffs argue that they have for all practical purposes been debarred from working with the Corps, without any process whatsoever. The Corps concedes that no process was afforded the plaintiffs. It argues that no process was due, as no de facto debarment occurred. Such de facto debarment claims are not unknown to the federal courts. See, e.g., Hellenic Am. Neighborhood Action Comm. v. City of New York, 101 F.3d 877 (2d Cir.1996) (acknowledging that a state employee's letter instructing agencies to reject all proposals by the plaintiff constituted a de facto debarment subject to due process requirements, but finding those requirements adequately fulfilled in the instant case); Old Dominion Dairy Prods., 631 F.2d at 961 n. 17 (stating that the plaintiff's "claim of de facto debarment is not frivolous" but passing over the issue as not properly presented to the court); TLT Constr. Corp. v. United States, 50 Fed.Cl. 212, 215-16 (2001) ("Two options exist to establish a de facto debarment claim: (1) by an agency's statement that it will not award the contractor future contracts; or (2) by an agency's conduct demonstrating that it will not award the contractor future contracts.") (citing CRC Marine Serv., Inc. v. United States, 41 Fed.Cl. 66, 84 (1998)); Leslie & Elliott Co. v. Garrett, 732 F.Supp. 191, 195, 198 (D.D.C.1990) (stating that a court can find a de facto debarment where there is either "a statement that the agency
The plaintiffs contend that their debarment constituted unlawful agency action under the Administrative Procedures Act ("APA"). Under the APA, 5 U.S.C. § 706, the court reviews final agency actions under an "arbitrary and capricious" standard to ascertain whether those decisions were made within the bounds of reasoned decision-making. Baltimore Gas & Elec. Co. v. Natural Resources Defense Council, 462 U.S. 87, 105, 103 S.Ct. 2246, 76 L.Ed.2d 437 (1983). The Corps urges that there was no de facto debarment and thus no final action to review. This court concluded in an earlier opinion that, in the event a de facto debarment was proved, such conduct would constitute final agency action triggering such review under the APA. (DN 35, p. 4 citing Air Brake Sys. v. Mineta, 357 F.3d 632, 639 (6th Cir.2004)); Cf. Peter Kiewit Sons' Co. v. U.S. Army Corps of Engineers, 714 F.2d 163, 168 (D.C.Cir.1983)(in dictum, de facto debarment constituted reviewable final agency action).
Previously, we denied the Corps' motion to dismiss, finding that the plaintiffs had stated a claim of de facto debarment. (DN 35, p. 5). The parties have now moved the court to test the claim under the summary judgment standard and determine whether de facto debarment occurred. We conclude that the undisputed fact are sufficient to establish that the Corps is entitled to summary judgment as a matter of law.
Plaintiffs must meet a high standard when seeking to prove a de facto debarment claim. "To succeed, [the plaintiff] must demonstrate a systematic effort by the procuring agency to reject all of the bidder's contract bids." TLT Const. Corp. v. U.S., 50 Fed.Cl. 212, 215 (2001). De facto debarment may be proved (1) by an agency's statement that it will not award the contractor future contracts; or (2) by an agency's conduct demonstrating that it will not award the contractor future contracts. TLT Const. Corp., 50 Fed.Cl. at 216.
The plaintiffs contend that comments made to Harris by McCafferty on April 2, 2008 establish de facto debarment of Hawkins from future contracts with the Corps. Harris testified that he made notes attempting to accurately document what occurred during the meeting. He took notes, and sent e-mails to a number of people in the days following the event, including more than one to Hawkins, recounting the conversation. Harris was admittedly very angry over the 9-month delay of his proposal, and what he perceived to be a veritable "squeeze play"
Harris' various versions of what McCafferty said to him are found in (1) purported contemporarily recorded notes, (2) an e-mail to Hawkins the following day, (3) an e-mail to Hawkins sent a week later, and (4) his deposition in 2011. What was actually expressed to Harris during the April 2, 2008 meeting is not entirely clear. However, Harris was not told that "the Corps wanted no proposals in which Hawkins played a role."
The most damning version of the encounter with McCafferty is contained in Harris' e-mail sent to Hawkins a week after the meeting. It is in this e-mail and his notes that Harris made this representation.
4/10/08 Harris. In this e-mail, Harris also assists Hawkins with a draft of a letter Hawkins proposed and ultimately sent to Nunn addressing the purported "blacklisting."
Harris testified that he stopped and made notes in the parking lot of Kentucky Oaks Mall immediately after meeting with McCafferty. He stated that this was an attempt to write down "everything I could remember, including her behavior, her rudeness, her condescension." (Harris Depo., p. 56). He stated in his notes, in pertinent part:
Harris Depo., pp. 63-65.
In an e-mail to Hawkins sent the day immediately following the meeting, however, Harris described a somewhat less direct communication by McCafferty, but termed it "blacklisting":
04/03/08 Harris e-mail to Hawkins.
When pressed in his deposition about the variances in his recollection of the McCafferty encounter, the following exchange took place:
Harris Depo., pp. 119-122.
When the meeting with McCafferty occurred, Harris was already dubious of the delay in the review of his proposal. He interpreted McCafferty's comments and mannerisms to indicate that Hawkins was being "blacklisted" by the Corps because of the Corps' prior lawsuit against him. Approximately 9½ months had already
Harris ultimately concluded that his project would not be accepted if he continued to use Hawkins as his consultant. Despite the fact that Hawkins received a letter from the Corps stating that Hawkins was free to work with anyone and that others were free to work with him on wetlands projects, Harris chose to replace Hawkins' firm with another firm which had previously been successful in wetlands projects with the Corps. Harris testified that he viewed the statements in the letter to Hawkins as "worthless," (Harris Depo., p. 125), and that the risk of further delay or rejection of his proposal was too great to continue his relationship with Hawkins. He stated in an e-mail in late April in which he severed his relationship with Hawkins that
A finder of fact reasonably could find that Harris had been presented with a fait accompli that his project would be rejected or would be mired in the process under "additional scrutiny" if he continued to utilize Hawkins as his consultant. It could as reasonably be concluded that McCafferty simply armed Harris with the facts from which he concluded that it was a bad business decision to pursue approval of his project with a consultant whose history would draw significant scrutiny by the Corps. Such a determination would first require a trial on the facts. However, no trial is warranted as we conclude that the claim would fail as a matter of law in any event.
The sum and substance of the plaintiffs' claim is that it was clearly implied to Harris that Hawkins' participation in this project was unwelcome. There was nothing stated or demonstrated by the Corps indicating that it would not grant Hawkins future contracts, beyond the one contract then before it. Harris' impressions concerned only the fate of his project, and he acted in accordance with his belief about the outcome of his project should he choose to proceed with Hawkins on board. In fact, the Corps represents that McCafferty fully intended to send the message that Hawkins' participation jeopardized the rate at which the approval process might progress or possibly its ultimate approval. However, McCafferty flatly denied making the statement that Ann Nunn told her that the Corps wanted no proposals in which Hawkins played a role. (McCafferty Depo., pp. 6-8). Harris admitted that the statement was not a quote. (Harris Depo., p. 120). Rather, Harris stated that it was his opinion that Hawkins
Even if it were proven at that Hawkins was prevented from obtaining the Harris contract with the Corps because he was removed from the project due to pressure placed on Harris by the Corps, such a finding would be insufficient to carry the day. Preclusion from a single contract is insufficient to establish de facto debarment. Dynamic Aviation, supra; TLT Const. Corp., supra; National Career College, Inc. v. Spellings, 371 Fed.Appx. 794 (9th Cir.2010); Redondo-Borges v. U.S. Dept. of Hous. and Urban Dev., 421 F.3d 1, 8-9 (1st Cir.2005).
The facts of this case can are readily distinguishable from the facts in Dynamic Aviation v. Department of Interior, 898 F.Supp. 11 (D.D.C.1995) on which the plaintiffs heavily rely. In Dynamic Aviation, the plaintiff had his aviation "cards" revoked for a period of one year. A pilot could not be re-issued "cards" until his pilot skills had been re-tested and his helicopter had been re-inspected. The Office of Aviation Services refused to perform the tests and inspection until a feral bureau specifically requested his services, but a pilot could not be awarded an informal contract unless he was "carded." The court found that this placed the pilot in a "Catch-22" where he could not obtain the needed card unless his services were requested, but his services would not be requested unless he had a card. The court stopped short of finding de facto debarment. Rather, summary judgment was denied, as the case presented genuine issue of material fact. In Dynamic Aviation, the agency prevented the pilot from meeting a legal prerequisite to participation in the bid process for contracts. Here, the plaintiffs have established that the Corps indicated that the Harris project would likely face a more difficult road to approval with Hawkins' involvement. There is simply no evidence, as there was in Dynamic Aviation, of a systematic effort by the agency to reject all of the plaintiffs' contract bids. Dynamic Aviation, 898 F.Supp. at 13; National Career College v. Spellings, 371 Fed.Appx. 794, 796 (9th Cir.2010); TLT Const. Corp., 50 Fed.Cl. at 215, Old Dominion Dairy Prods., supra, Leslie & Elliott Co., supra.
As the plaintiffs cannot establish de facto debarment, there was no final agency action subject to review under the APA. The plaintiffs are thus unable to prove their claim, and Count I as asserted against the Corps must be dismissed.
Summary judgment in favor of the Corps will be granted and summary judgment in favor of Hawkins and Highview will be denied. A separate order will be entered in accordance with this opinion.